Merlin Project does not support this concept. Percentaged lags on dependencies were ignored.
Merlin Project does not support blank lines between tasks, as the various sorting and grouping functions would repeatedly conflict with blank lines. Note that outline or WBS codes can always be used as a stable reference to activities. Subsequent row numbers were changed by this. This shows in detail the values that were not imported into Merlin Project due to different calculations or data structures. In order to calculate the values contained in them anyway, they are stored on the base costs. There are no cost resources in Merlin Project. However, their assignment costs have been converted into base costs. Since the concepts of both programs are quite different in individual cases, one or more messages may appear in Merlin Project after importing an MS Project file: MS Project users open Project XML Files thus. To export, call File -> Export -> MS Project. Merlin Project also supports export in Project XML files.